How to Choose a Submersible Sewage Pump

Flood control depends on pumps. Sandbags block water and flood barriers seal it out, but water that has already seeped or flowed in still has to be pumped away. A submersible sewage pump is the most common flood-drainage device, used in basements, underground car parks and construction foundation pits — but pump selection takes care: too little flow or head and the water cannot be cleared, too much and it wastes electricity and money, and may even damage the pipework. This article explains WQ submersible sewage pump selection, installation and pre-flood test runs under the current standard.

Know the Standard First: GB/T 24674-2021

The national standard for sewage and waste-water submersible electric pumps is GB/T 24674-2021, Sewage and Waste Water Submersible Electric Pumps, published 30 April 2021 and in force from 1 November 2021, replacing GB/T 24674-2009. The standard sets out the type, model, basic parameters, technical requirements, test methods, inspection rules and marking, packaging, storage and transport of sewage and waste-water submersible electric pumps.

The standard applies to single-phase or three-phase sewage and waste-water submersible electric pumps that convey sewage or waste water, or mixed liquids containing insoluble solids such as silt, fibre, faeces and river mud. Flood water is often mixed with silt and debris — exactly within this pump's scope. Write the full standard number, GB/T 24674-2021, on the purchase contract and acceptance sheet.

What Does WQ Mean?

WQ is the most common model code for sewage and waste-water submersible electric pumps: W stands for sewage (wushui) and Q stands for submersible (qianshui). A WQ pump is a non-clog submersible sewage pump whose impeller uses a flow-channel structure that passes media containing short fibres, paper scraps, silt and other solid particles without easily clogging.

A WQ pump consists of a submersible motor and a sewage pump: the motor sits on top and the pump below, with a mechanical seal plus a skeleton oil seal between pump and motor, and O-ring oil-resistant rubber seals at each fixed joint as static seals. The whole unit works submerged, takes little floor space, and is easy to install and use.

Choosing a WQ pump for flood drainage is right, and a clean-water pump cannot drain sewage. A clean-water pump's impeller channel is narrow — silt and debris clog it at once, and in serious cases burn out the motor. Flood water contains all sorts, so a sewage pump is a must.

The Two Key Selection Parameters: Flow and Head

Choosing a pump means looking at two parameters, and neither can be skipped:

  • Flow: how much water it can drain per hour, in cubic metres per hour. Set flow by drainage demand: basement area, water inflow speed and how fast the water must be cleared all count. Too little flow and the water keeps rising; too much flow and electricity costs rise and pipe pressure grows. When buying, give the site details and let the supplier or a professional work it out — do not buy by feel.
  • Head: how high the pump can lift water, in metres. Work head out from the drainage distance and height difference: the vertical height from the sump to the discharge point, plus pipe friction losses along the way. Too little head and the water cannot be discharged; too much head and flow actually falls while electricity is wasted. Head and flow affect each other — choose from the performance curve, not only from the maximum values on the nameplate.

Installation and Electrical Safety

A submersible sewage pump is installed in one of two ways. Fixed installation uses an automatic coupling device, so pump and pipework connect automatically and the pump can be lifted out for servicing — suited to fixed points such as sumps and pump stations. Mobile installation puts the pump straight into the water, connects the discharge hose and starts pumping — suited to temporary drainage and emergency rescue.

Electrical safety is the top priority — a submersible pump works in water, so a leak is a serious matter:

  • Reliable earthing is a must before use, with a residual-current device fitted. Without reliable earthing or a residual-current device, the pump must not go into the water.
  • Cables must not be damaged, and joints must not sit in water. A damaged cable or a joint that lets water in carries a large leakage risk.
  • Never move the pump while it is powered — cut the power first.
  • No people or animals should come near the pump body, and do not test it by hand while it is running.

The standard also sets insulation requirements: GB/T 24674-2021 states that the cold-state insulation resistance of a pump motor stator winding to the casing, at 660 V and below, should be no less than 50 MΩ. Low insulation resistance means the motor is damp and a seal may be faulty — investigate, dry it, retest until it passes, and only then put it in the water.

Pre-Flood Test Run and Maintenance

Do not put a newly bought pump straight into storage — power it up and test-run it once, confirming it starts normally, drains normally and makes no abnormal noise or vibration. Deal with any problem found in the test run at once; do not wait until the flood season to repair it.

Do a full check before the flood season: power-on test run, insulation resistance check, checks of cables, seals and impeller, and checks that the discharge hose and power cable are complete. Check once a month during the flood season, and count and top up after the flood season. A pump left unused for a long time should be cleaned and dried before storage, and kept in a dry place. For the wider flood stock list, see Flood Control Supplies: Company and Community Stock List.

A pump left sitting still that will not start at the critical moment is the most common problem. A pre-flood test run is not a formality — it really means powering up and really draining water, confirming that every link works.

Frequently Asked Questions

What size pump should I buy for draining an underground car park?

Choose by drainage demand and head: basement area, water inflow speed and drainage distance all matter. Give the supplier or a professional the site details and let them work it out — do not buy by feel.

What is the difference between a WQ pump and a clean-water pump?

A WQ pump is a non-clog submersible sewage pump with a wide impeller channel that passes silt, fibre and other solid particles; a clean-water pump has a narrow channel and can only pump clean water. Flood water contains all sorts, so a sewage pump is a must.

How often should a water pump be checked?

Do a full check before the flood season — power-on test run, insulation resistance test, and checks of cables and seals; check once a month during the flood season; and count and top up after the flood season. Before long-term storage, clean and dry it.

What should I do if the insulation resistance fails?

Under GB/T 24674-2021, the cold-state insulation resistance of a pump motor stator winding to the casing at 660 V and below should be no less than 50 MΩ. A failed reading means the motor is damp or a seal may be faulty — investigate the damp and the seal, dry it, retest until it passes, and only then put it in the water.